Paducah Public Schools – Guaranteed Energy Savings Contract – Phase II

Paducah, Kentucky

In Brief: The Project at a Glance

Paducah Public Schools implemented Phase II of its Guaranteed Energy Savings Contract program to continue improving infrastructure across district facilities.

  • The project focused on modernizing aging building systems and improving overall energy performance.
  • AFP developed a districtwide energy strategy that bundled multiple infrastructure improvements into a coordinated project.
  • The improvements generate substantial annual energy savings while improving system reliability and facility performance.

Why We Were Called

Paducah Public Schools sought to build on earlier facility improvements by continuing to modernize building infrastructure across district schools.

Many facilities still relied on aging HVAC systems, outdated lighting infrastructure, and inefficient building systems that increased operating costs and maintenance demands. District leadership wanted to continue improving facility performance while maintaining predictable operating expenses.

AFP was engaged to identify additional energy-efficiency opportunities and implement a second phase of the district’s energy savings strategy.

Key Achievements

  • Implemented Phase II of the district’s Guaranteed Energy Savings Contract program
  • Addressed infrastructure improvements across multiple district schools
  • Upgraded HVAC systems and lighting infrastructure
  • Improved building automation capabilities
  • Implemented solar photovoltaic generation
  • Reduced annual utility costs by approximately $248,000

Setting the Stage

Paducah Public Schools operates multiple facilities that rely on mechanical systems and building infrastructure to maintain safe and comfortable learning environments.

Over time, aging equipment and inefficient systems increased energy consumption and maintenance costs across district buildings. District leadership recognized the need for a coordinated strategy to modernize infrastructure while maintaining responsible financial planning.

Our Approach

AFP worked with district leadership to develop Phase II of the district’s Guaranteed Energy Savings Contract program, focusing on identifying additional opportunities for energy efficiency and infrastructure improvements.

By bundling multiple upgrades into a comprehensive project, the district was able to modernize facilities while generating energy savings that help offset project costs.

The Work: Scope of Improvements

HVAC Systems

  • Replacement and refurbishment of aging HVAC equipment

Lighting Upgrades

  • Conversion to high-efficiency LED lighting across district facilities

Building Automation Controls

  • Expansion and optimization of building automation systems

Solar PV

  • Installation of solar photovoltaic generation

Thermal Envelope Improvements

  • Building envelope improvements to reduce heating and cooling losses

Water Conservation Measures

  • Implementation of water-saving improvements across facilities

Results: Measured Impact

The project produced measurable improvements in facility performance and operational efficiency.

  • Approximately $248,000 in annual energy savings
  • Improved reliability of mechanical systems
  • Reduced long-term operational and maintenance costs
  • Improved energy efficiency across district facilities
  • More stable and predictable operating expenses

What’s Next?

With the successful completion of Phase II improvements, Paducah Public Schools has strengthened the performance and reliability of its facility infrastructure.

The district can continue building on these improvements through future energy-efficiency initiatives and infrastructure upgrades that further enhance learning environments while maintaining responsible operational planning.

Project Type

Guaranteed Energy Savings Contract (GESC) – Phase II

Start Date

April 18, 2022

Finish Date

2023

Facilities

  • Districtwide facilities
  • Paducah Tilghman High School
  • Paducah Middle School
  • Clark Elementary School
  • Morgan Elementary School
  • McNabb Elementary School

Major Upgrades

  • HVAC replacement and refurbishment
  • LED lighting upgrades
  • Building automation controls
  • Solar PV installation
  • Thermal envelope improvements
  • Water conservation measures

Annual Energy Savings

Approximately $248,000

Project Cost

$10,362,303

Total Square Footage

491,970

Client

Paducah Public Schools

Lead Project Designer

Russ R. Litsinger,
Ascendant Facility Partners

Superintendent

Dr. Donald Shively

Consultants

JRA Architects
Marcum Engineering

General Trades Contractor

Ray Black & Son

Mechanical Contractor

Triangle Enterprises

Status

Project complete